Khaleej Times, Sunday, Mar 05, 2023 | Sha'ban 13, 1444
Dubai: Buying off-plan property? Laws, investors' rights explained
Emirates:
Question: I am planning to invest in an off-plan property in Dubai.
What happens if the developer fails to deliver the property? What are my rights
in this regard?
Response: In Dubai, any off-plan property sold by a developer needs to
be registered in the Interim Real Property Register maintained by the Dubai Land
Department (DLD). This is in accordance with Article 3(1) of the Dubai Interim
Real Property Register Regulations.
Further, Article 4 (1) of the Dubai Interim Real Property Register Regulations
states: “A master developer or sub-developer may not commence the implementation
of a project or sell its units off-plan unless it takes possession of the land
on which the project is to be constructed and obtains the necessary approvals
from the competent entities in the emirate.
“In all events, the DLD must create an entry on the registry folio of the real
property to denote it is being developed."
Based on the aforementioned provision of law, once you find a suitable property,
you may verify if the developer of the property has registered the project with
the DLD. A developer may not enter into any sale contract with a purchaser until
it obtains relevant approvals from the DLD. This is as mentioned in Article 10
of the Dubai Interim Real Property Register Regulations.
In case the developer fails to deliver the property you purchased in accordance
with the terms of the Sale Purchase Agreement (SPA), you may request it to
fulfil its obligations. If the developer does not comply, you may approach the
DLD and file a complaint.
Are Dubai apartment prices expected to rise further?
The DLD may attempt to settle the matter amicably between you and the
developer. This is in accordance with Article 14 of the Executive Council
Resolution No. 6 of 2010, which states: “Where any dispute arises between a
developer and a purchaser, the DLD may undertake conciliatory efforts to
preserve their contractual relationship and may propose any solutions it deems
appropriate to achieve this objective. Where the developer and the purchaser
reach an amicable settlement, that settlement shall be documented in a written
agreement executed by the developer and the purchaser or their respective
representatives. Upon approval of that agreement by the DLD, it shall become
binding to both parties."
The Real Estate Regulatory Agency of Dubai (Rera) may also cancel the project
on technical grounds, if a developer does not fulfil conditions — such as
failing to commence construction work without a valid reason; if the authority
is satisfied that the developer has no genuine intention (good faith) to
continue with the project; failure by the developer to implement the project due
to gross negligence, etc. This is in accordance with Article 23 of the Executive
Council Resolution No. 6 of 2010.
Further, a developer needs to refund all the payments made by a purchaser if the
project is cancelled by the decision of Rera. This is in accordance with Article
11(b) of Dubai Amended Interim Real Property Registration Regulations of 2017.
In the event the developer does not refund the payments, then the Rera may take
all necessary actions to preserve your right as a purchaser. This is in
accordance with Article 27 of the Executive Council Resolution No. 6 of 2010,
which states: “If the developer fails to refund the amounts owed to the
purchasers within the period set forth in Article 26 (60 days) of this
resolution, Rera must take all necessary actions to preserve the rights of
purchasers including referring the matter to the competent judicial
authorities."p>
You as a purchaser may also approach the competent court in Dubai to seek
termination of the SPA. This is in accordance with Article 20 of the Executive
Council Resolution No. 6 of 2010. However, a developer may have protection under
Article 21 of the Executive Council Resolution No. 6 of 2010 if the reasons for
handing over of the property is delayed due to reasons beyond the control (force
majeure) such as property taken over by authorities in the interest of the
public; if authorities suspend the project for replanning purposes, etc.